HUD construction draws and change orders: how money moves on a 221(d)(4)

On a HUD 221(d)(4) loan with insurance of advances, the contractor requisitions monthly on form HUD-92448, a HUD inspector confirms the work, and the lender approves each interim draw; HUD approves only the initial and final advances. The contractor's 10% retainage can step down to 5% after 50% completion and 2.5% after 75%, and every change order needs written lender and HUD approval before the work starts.

Two ways HUD insures a construction loan

A 221(d)(4) deal is closed one of two ways, and the draw process depends on which.

Insurance of advances Insurance upon completion
What HUD insures Each construction draw, from initial endorsement Only the permanent loan, at final endorsement
Who funds construction The HUD lender, through insured advances A separate construction lender
HUD monthly requisitions Yes (HUD-92448) Not applicable
HUD inspections Monthly, for progress, quality, wages and fair housing For labor, fair housing and plan compliance only
Escrow for additive change orders Required once changes reach $5,000 Not required; borrower must have the funds
MIP From initial endorsement Not charged until final endorsement
Latent defects assurance Contractor warranty and latent defects agreement 2.5% of construction cost, cash or letter of credit, for 15 months

Under insurance upon completion HUD has no risk until final endorsement, so it does not monitor the lender’s disbursements or step into construction disputes (MAP 12.16). Most of this guide is about insurance of advances, where HUD’s rules govern every dollar.

Before the first draw: the pre-construction conference

Every new construction and substantial rehabilitation project must hold a pre-construction conference before construction starts, including an early start (MAP 12.2). It is run by the HUD inspector or HUD construction analyst and attended by the borrower, its supervisory architect, the general contractor, major subcontractors (any principal trade, or any with 15% or more of the hard cost), HUD’s underwriter, the lender and HUD’s Davis-Bacon and Labor Standards staff.

The conference covers how draws, change orders, stored materials, retainage, permission to occupy and cost certification will work. Two rules from it trip up first-time HUD developers:

  • Work done in anticipation of a change order is noncompliant. There are no insured advances for it, or for other work that depends on it.
  • Identities of interest that appear after closing must be reported to the lender and HUD within 5 working days, identity-of-interest subcontractors need HUD’s prior approval, and shell general contractors are prohibited.

For a 223(f) the conference is optional, depending on size, repair scope and the team’s experience.

The monthly draw cycle

  1. Monthly job meeting. The contractor, borrower, supervisory architect and HUD inspector meet on site each month when the draw request is prepared (MAP 12.3.5). The architect keeps the minutes. The lender must also attend when construction falls more than 10% behind the progress schedule (form HUD-5372) or other problems threaten completion.
  2. Contractor’s requisition. The contractor submits form HUD-92448 for work completed and materials stored, with bills and receipts.
  3. HUD inspection. The HUD inspector, usually an independent third party under contract to HUD, visits at least once a month (MAP 12.3.4.3), checks that the amounts requested are reasonable, interviews workers on form HUD-11 and records the visit on the Trip Report, form HUD-95379.
  4. Lender approval. The lender’s construction loan administrator signs forms HUD-92403 and HUD-92448 for interim advances. HUD’s Regional Production Director signs the initial and final advances (MAP 12.7.1).
  5. Title. The lender confirms clear title before funding and tells HUD in writing if mechanics liens stay unresolved for more than 60 days (MAP 12.7.2).

Some rules apply to every advance:

  • Equity first. Escrowed funds for on-site improvements must be spent before mortgage proceeds. Government grant or loan proceeds and tax credit equity can be the exceptions (tax credit equity can go in pro rata under chapter 14); EB-5 money cannot and must be funded up front like other equity.
  • Draws follow progress. Construction funds advanced must match progress as approved by the HUD inspector, and other mortgageable items need bills or receipts.
  • Wages travel with the draw. Each request for advances carries a certification of compliance with Davis-Bacon wage rates. Contractor payrolls go directly to HUD’s Labor Standards and Enforcement staff at least monthly (MAP 12.12.1). The weekly certified payroll mechanics are on the Davis-Bacon page.

Retainage

The HUD construction contract holds back 10% of each monthly payment for completed work and stored materials (MAP 12.15.5). It can step down if three conditions hold: the contractor has no more than a 5% equity interest in the borrower, the surety consents in writing, and HUD has no questions about quality, contract compliance or open change orders.

Stage of completion Retainage, eligible contractor
Up to 50% 10%
50% to 75% 5%
75% to final endorsement 2.5%
  • Identity-of-interest contractors (more than 5% of the ownership) generally keep the full retainage until final endorsement.
  • Early partial release is possible after 90% completion with a request from the contractor, borrower and lender and surety consent, but the undisbursed holdback must stay at or above 2.5% of the contract amount.
  • Projects in difficulty can get part of the holdback before 90% only to prevent a default of the construction loan, and only if that would get the project finished.

Next-to-final and final advances

The next-to-final advance can be requested once construction is acceptably complete, even with items of delayed completion. For a non-identity-of-interest contractor it releases the retainage, subject to the contractor’s cost certification having been reviewed, certificates of occupancy and HUD’s Permission to Occupy (form HUD-92485) for all units, all Davis-Bacon payroll requirements met, and the survey submitted. HUD still keeps back enough for delayed items (150% of HUD’s estimate), lien claims, liquidated damages and any negative net change orders (MAP 12.15.5.D).

The final advance releases the remaining mortgage proceeds after HUD has approved the cost certification and set the maximum insurable mortgage on form HUD-92580 (MAP 12.7.7). Items of delayed completion go into an escrow of at least 150% of the estimated cost, capped at 2% of the mortgage, and must be finished within 12 months of the final HUD inspection (MAP 12.6.2). Final closing cannot happen until HUD’s labor standards staff give written clearance on wages (MAP 12.12.2).

Change orders

Any change to the scope, price or time of the construction contract is requested on form HUD-92437, signed by the borrower, its architect, the general contractor and the lender, then reviewed by HUD (MAP 12.8.1). HUD aims to process a change request in no more than 5 workdays (MAP 12.9.1).

HUD approves a change only if it fits one of three classes (MAP 12.8.2):

Class What qualifies
Necessary Latent site conditions that differ from the documents, code changes after closing (or after firm commitment for insurance upon completion), architect errors or omissions, damage to completed work
Betterment Economically justified: raises net income, lowers long-term operating or maintenance cost, or otherwise strengthens the security
Equivalent A substitute for an item that is not available, or a cheaper substitute with equal or better performance

How each kind is funded:

  • Additive changes. Except for necessary changes, the borrower escrows the cost of an additive change order once HUD estimates the aggregate increase reaches $5,000, and of every additive change after that (MAP 12.8.3). A letter from the contractor confirming the borrower has paid can stand in for the escrow. Nonprofit borrowers can use the developer fee. After 75% completion, on schedule and with no noncompliance findings, HUD may let approved additive changes come from the 2% construction contingency.
  • Price disagreements. If the contractor’s estimate exceeds HUD’s, the difference is escrowed; if HUD’s estimate is higher, HUD’s excess is held until final endorsement (MAP 12.11.2).
  • Deductive changes. While the aggregate decrease stays under 2.5% of the contract price, the lender cuts the contractor’s final requisition. At 2.5% or more, the decrease shows on every requisition and the mortgage is reduced at cost certification where required (MAP 12.8.4).
  • Changes that cut income. These are grounds for rejection unless the change is necessary and unavoidable; if HUD’s re-underwriting produces a smaller loan, later requisitions are reduced (MAP 12.8.5, 12.11.2).
  • Changes caused by error or negligence of the architect, owner or contractor are recorded as such and their cost stays out of the mortgage (MAP 12.8.11).
  • Unapproved changes. The inspector reduces the requisition for the noncompliant work and for any removal it may require (MAP 12.9.3).

The only change that can be made before approval is an emergency that endangers life or property or halts construction (MAP 12.8.8). Change orders submitted after the final HUD Trip Report are not approved unless they concern items of delayed completion or the Regional Production Director agrees in writing. Any physical change must also leave the environmental review and its mitigation conditions intact.

Time extensions and keeping the loan in balance

The lender can approve a time extension only when the delay is beyond the contractor’s control (strikes, unknown site conditions, weather worse than the seasonal average), it is requested on time under the contract, and the surety consents in writing (no surety consent is needed where completion is assured by cash or a letter of credit) (MAP 12.8.6).

HUD prices an extension mechanically: 65% of the contractor’s monthly general requirements cost per month, a quarter of that per week, and nothing for extensions under a week. Carrying costs are pro-rated daily from the underwriting, and an extra year of MIP is due if the extension pushes the construction term past 12, 24 or 36 months (MAP 12.10.2, 12.11.2).

If the delay is the contractor’s fault, extra interest, taxes, insurance and MIP are paid through the liquidated damages clause. HUD treats the interest budget as overspent when the share used runs 10% or more ahead of the share of construction completed (MAP 12.7.8). The liquidated damages amount is then moved from the construction line to carrying charges, with notice to the borrower, contractor and surety.

Escrows that sit beside the draws

Escrow Size and use Release
Working capital (HUD-92412M) 4% of the mortgage on new construction, half of it (2%) a contingency for approved change orders and overruns not caused by the contractor; rent-up costs and first-year shortfalls Unused working capital portion after 6 consecutive months of sustaining occupancy, with HUD approval
Initial operating deficit Covers expenses and debt service during lease-up; not mortgageable Unused amount after 6 consecutive months of sustaining occupancy
Cash-out from land equity Land equity above what was needed at initial endorsement is deferred After 6 months of sustaining occupancy (12 months for large loans)
Items of delayed completion At least 150% of cost, at most 2% of the mortgage As items are finished, within 12 months

Sources: MAP 12.8.1.A.5, 12.15.3, 12.15.4, 12.15.6, 12.6.2. Working capital cannot pay hard construction costs. Insurance upon completion deals need the working capital and operating deficit escrows too, but not the extra 2% contingency (MAP 12.16.M).

Occupancy before completion

Units can be leased before the whole project is done. The borrower, supervisory architect, contractor, lender and HUD sign a Permission to Occupy, form HUD-92485, backed by a certificate of occupancy and evidence of property and liability insurance (MAP 12.14). HUD favors partial occupancy building by building or floor by floor where it brings in needed income and earlier rent-up. Dwelling units with open punch-list items are not accepted for occupancy; punch-list items in common areas and outside do not block it (MAP 12.6.1).

Repairs on a 223(f) or 223(a)(7)

A purchase or refinance with repairs follows a lighter version of the same rules (MAP 12.17):

  • Critical repairs are finished and confirmed by a HUD site visit before closing. Only critical accessibility repairs HUD approves for deferral can wait.
  • Non-critical repairs can be deferred, normally finished within 12 months, and paid from a repair escrow holding the full cost plus a 10% or 20% assurance of completion. Releases are against a schedule of values, for completed hard costs; soft costs follow pro rata.
  • Inspection depends on scope. 223(a)(7) work and 223(f) work limited to repairs and Level 1 alterations can be self-certified. Level 2 alterations get periodic inspections unless waived. Work needing a project architect (over $15,000 per unit, or Level 2 and 3 alterations) is inspected at 35%, 65% and 100%.
  • Change orders after closing that add cost are funded by the borrower when approved, and the repair escrow is never reduced for changes that save money. Total repairs must stay under the substantial rehabilitation threshold.
  • Leftover escrow goes back to the borrower once HUD confirms the repairs and title; where repairs exceed $400,000, a latent defects assurance of 2.5% of the repair cost is held for 15 months first.
  • If repairs are not finished by the deadline, the lender completes them with the escrow funds and returns what is left, less its costs.

Davis-Bacon does not apply to 223(f) repairs; see 223(f) and the Davis-Bacon page.

Sources

  1. HUD MAP Guide, Handbook 4430.G, 2020 edition, chapter 12 (Construction Period): 12.2, 12.3, 12.6, 12.7, 12.8 to 12.11, 12.12, 12.14 to 12.17
  2. HUD MAP Guide, 2020 edition, 3.2.5 Cost Certification and 3.2.6 Federal Labor Standards
  3. 24 CFR 200.95, Certification of cost requirements
  4. 24 CFR 200.33, Labor standards (FHA multifamily)

Checked against these sources on October 31, 2026. HUD changes program rules by Mortgagee Letter and Federal Register notice; the lender's commitment governs any loan.

Short answers

How often can you draw on a HUD 221(d)(4) construction loan?

Monthly. The contractor prepares a requisition on form HUD-92448 for the monthly job meeting, the HUD inspector checks the amount against the work in place, and the lender approves the interim advance on form HUD-92403. HUD approves the first advance at initial endorsement and the final advance itself. Any equity or other escrowed funds for on-site work generally have to be spent before mortgage proceeds.

What is the retainage on a HUD construction loan?

The construction contract holds back 10% of each monthly payment. After 50% completion it can drop to 5%, and after 75% to 2.5% until final endorsement, but only if the contractor owns no more than 5% of the borrower, the surety consents in writing and HUD has no concerns about the work. A contractor with a larger identity of interest keeps the full retainage until final endorsement.

Do change orders need HUD approval?

Yes. Every change to scope, price or time goes on form HUD-92437, signed by the borrower, architect, contractor and lender, and HUD must approve it before the work is done. Work done ahead of an approved change order is treated as noncompliant and is not paid from insured advances. The only exception is an emergency that endangers life or property or halts construction, and the paperwork must follow as soon as possible.

Will HUD increase the loan if a change order raises the cost?

Not during construction, and the lender is told not to promise one. Except for necessary changes, the borrower escrows the cost of additive change orders once they total $5,000 or more. A mortgage increase can only be requested after completion and cost certification, for specific reasons such as differing site conditions or code changes, never for ordinary cost overruns.

Who pays if construction runs late?

If the delay is the contractor's fault, extra interest, taxes, insurance and MIP are funded through the liquidated damages clause in the HUD construction contract. If the delay is beyond the contractor's control, the lender can approve a time extension and require the added carrying costs to be funded from cash, excess mortgage proceeds, the contingency or a nonprofit developer fee. A long enough extension can add a further year of MIP.

How do repairs get paid on a 223(f) loan?

Critical repairs are finished and inspected before closing. Non-critical repairs can be completed after closing, usually within 12 months, and are paid out of a repair escrow that holds the full cost plus an extra 10% or 20%. Small scopes can be self-certified by the owner; work large enough to need a project architect is inspected at 35%, 65% and 100% complete.

Get a quote

Tell the desk about the property. Two steps, about two minutes.

Step 1 of 2 · The deal
About the deal
Minimum loan amount is $1M. An estimate is fine.
Your contact information

Contact information

Your information goes to our capital markets desk only. It is never sold, and no lender sees your deal without your go-ahead. Submitted over an encrypted connection.

Getting commercial property financing should be easy. Now it is. Click below for a free, no obligation quote and to learn more about your loan options.

Get a quote
Call Get a quote